+1

> On Jul 9, 2020, at 1:18 PM, Udo Kohlmeyer <u...@vmware.com> wrote:
> 
> Hi there Geode Dev's
> 
> I would like to propose the following changes to the RFC process that we have 
> in place at the moment.
> 
>  1.  All submitted RFC’s will provide a minimum 2 week review period. This is 
> to allow the community to review the RFC in a reasonable timeframe. If we 
> rush things, we will miss things. I’d rather have a little more time spent on 
> the RFC review and getting the approach “correct” than rushing the RFC and 
> then at a later point in time (either at PR review or worse production issue) 
> find out that the approach was less than optimal.
>  2.  Add a new section to the RFC. I would like to propose this section to be 
> labelled “Use Cases”. In this section I would like all submitters to describe 
> the use case that this RFC is to fulfill. This would include all possible 
> combinations (success and failure) and expected outcomes of each.
> 
> I hope with the additions to the RFC process and template we can better round 
> out each RFC. Causing less delays later in the process and allowing all 
> community members to actively participate in the review process regardless of 
> technical skill level.
> 
> Thoughts or comments?
> 
> —Udo