On Sunday, August 19, 2012 12:50:18 Cyrille Berger Skott wrote: > On Sunday 19 Aug 2012, Inge Wallin wrote: > > On Tuesday, August 07, 2012 10:10:14 Cyrille Berger Skott wrote: > > > Hi, > > > > > > Here is the suggested schedule for 2.6: > > > > > > September 7th alpha tagging > > > September 28th branch+beta tagging > > > October 19th RC tagging > > > > > > Release expected early November > > > > I have a problem with this schedule. > > > > Calligra 2.5 was released august 13th. A release of 2.6 means that the > > development time will be less than 3 months, a pretty far cry from the 4 > > month schedule that was announced suggested. > > Indeed... There was a bug in my schedule, it should be: > > October 5th alpha tagging > October 26th branch+beta tagging > November 26th RC tagging
Now we're talking! :) I approve this schedule. _______________________________________________ calligra-devel mailing list calligra-devel@kde.org https://mail.kde.org/mailman/listinfo/calligra-devel