Thanks Jonathan, We will have a try.
2010/6/30 Jonathan Ellis
> On Mon, Jun 28, 2010 at 10:11 PM, albert_e wrote:
> > Hi, all
> >
> > We have several nodes in DC1 and DC2 and we want to move all nodes in DC2
> to
> > a new DC3, also IPs will be changed. The whole progress will last about
> 1-2
On Mon, Jun 28, 2010 at 10:11 PM, albert_e wrote:
> Hi, all
>
> We have several nodes in DC1 and DC2 and we want to move all nodes in DC2 to
> a new DC3, also IPs will be changed. The whole progress will last about 1-2
> days.
>
> Can we simply stop all nodes in DC2, move to DC3, chage IP config i
Hi, all
We have several nodes in DC1 and DC2 and we want to move all nodes in DC2 to
a new DC3, also IPs will be changed. The whole progress will last about 1-2
days.
Can we simply stop all nodes in DC2, move to DC3, chage IP config in
storage-conf.xml then start all nodes in DC3?
Or shall we do