[ACTIVITY] report week 02
RAG: Red: Amber: Green: good progress on A15 vexpress system model Current Milestones: || || Planned|| Estimate || Actual || ||cp15-rework || 2012-01-06 || 2012-02-20 |||| ||initial-a15-system-model || 2012-01-27 || 2012-01-27 ||
[ACTIVITY] report week 02
RAG: Red: Amber: Green: issues I wanted to nail at this sprint all handled; a couple of blueprints handed off to other people Milestones: | Planned| Estimate | Actual | finish virtio-system | 2010-08-27 | postponed || finish testin