Re: JK 1.2.29 Plan

2010-02-10 Thread Mladen Turk
On 02/08/2010 08:32 AM, Rainer Jung wrote: After a couple of heavily loaded weeks, I'll have time to care about it this week. I'll review the changes done by Mladen and will then proceed with the usual snapshot for letting people do some tests before the final release. I guess I'll need 2 or 3 da

Re: JK 1.2.29 Plan

2010-02-10 Thread Mladen Turk
On 02/08/2010 08:32 AM, Rainer Jung wrote: After a couple of heavily loaded weeks, I'll have time to care about it this week. I'll review the changes done by Mladen and will then proceed with the usual snapshot for letting people do some tests before the final release. I guess I'll need 2 or 3 da

Re: JK 1.2.29 Plan

2010-02-07 Thread Rainer Jung
y, 2010 12:42:07 AM GMT +12:00 New Zealand Subject: Re: JK 1.2.29 Plan +1 I've done majority of planned fixes. Let's tag and then play with IIS rotatelogs. BTW, the IIS logging should be fixed now (compiling with commode.obj that forces a real flush on fflush) On 01/06/2010 11:07 AM, R

Re: JK 1.2.29 Plan

2010-02-07 Thread Tim Whittington
I guess we need to re-plan this since we missed the dates? I'll hold off on the IIS log rotation changes until 1.2.29 is tagged. cheers tim From: "Mladen Turk" > To: dev@tomcat.apache.org > Sent: Thursday, 7 January, 2010 12:42:07 AM GMT +12:00 New Zealand > Subject: R

Re: JK 1.2.29 Plan

2010-01-06 Thread Mladen Turk
+1 I've done majority of planned fixes. Let's tag and then play with IIS rotatelogs. BTW, the IIS logging should be fixed now (compiling with commode.obj that forces a real flush on fflush) On 01/06/2010 11:07 AM, Rainer Jung wrote: Any objections to the following plan about JK 1.2.29? - 15.

Re: JK 1.2.29 Plan

2010-01-06 Thread Peter Roßbach
+1 Regards Peter Am 06.01.2010 um 11:07 schrieb Rainer Jung: Any objections to the following plan about JK 1.2.29? - 15.01.2009 make snapshot available for testing feedback like we did for nearly all previous releases - ~22.01.2009 tag 1.2.29 (exact date depending whether there's bug feed

Re: JK 1.2.29 Plan

2010-01-06 Thread Henri Gomez
+1 2010/1/6 Rainer Jung : > Any objections to the following plan about JK 1.2.29? > > - 15.01.2009 >  make snapshot available for testing feedback like we did >  for nearly all previous releases > > - ~22.01.2009 >  tag 1.2.29 (exact date depending whether there's bug feedback) > > Regards, > > Ra

JK 1.2.29 Plan

2010-01-06 Thread Rainer Jung
Any objections to the following plan about JK 1.2.29? - 15.01.2009 make snapshot available for testing feedback like we did for nearly all previous releases - ~22.01.2009 tag 1.2.29 (exact date depending whether there's bug feedback) Regards, Rainer