Re: Release process

2011-04-16 Thread Cyrille Berger Skott
Hi, Thanks for the email :) Hopefully after this week-end, I will have time and energy to do the coordination work :) Anyway, I have put todo list and tentavive schedule on the wiki: http://community.kde.org/Calligra/Schedules/2.4/Release_Plan#2.3.71 -- Cyrille Berger Skott __

Re: Release process

2011-04-16 Thread Boudewijn Rempt
On Saturday 16 April 2011 Apr, Boudewijn Rempt wrote: > Hi! > > As decided at the Calligra sprint, Hannah, Boudewijn, Cyrille and Inge have > sat together to dicuss the snapshot release and what needs to be done for > that. We wanted to release about three weeks after the sprint. We need help >

Release process

2011-04-16 Thread Boudewijn Rempt
Hi! As decided at the Calligra sprint, Hannah, Boudewijn, Cyrille and Inge have sat together to dicuss the snapshot release and what needs to be done for that. We wanted to release about three weeks after the sprint. We need help with a number of things though: * We need a good visual guide f