Re: 2.4 release schedule

2011-07-11 Thread C. Boemann
On Monday 11 July 2011 18:08:58 Cyrille Berger Skott wrote: > Hi, > > There was a discussion on IRC about it a little while ago about the release > schedule, one of the conclusion was that soft-freeze was not needed > anymore. > > But some people thought that the freezing time would be too long,

Re: 2.4 release schedule

2011-07-11 Thread Cyrille Berger Skott
Hi, There was a discussion on IRC about it a little while ago about the release schedule, one of the conclusion was that soft-freeze was not needed anymore. But some people thought that the freezing time would be too long, so here is an alternative schedule. August 31th -> soft freeze, n

2.4 release schedule

2011-06-22 Thread Cyrille Berger Skott
Hi, I am proposing the following release schedule: July 13th -> soft-freeze, all features need to be noted down in the feature plan August 31th -> hard freeze, no more features in master September 7th -> beta1 is tagged, master is branched into "