Hello everyone, I know 7.0.1 isn't out the door yet, and 8.0.0 isn't due for a while, so relax :-) But I would like to get the schedule decided before folks disappear over the holidays.
According to the usual schedule, the branch would be created two weeks into January, with the goal of shipping early March, so this is my proposal: - 16 January 2019: Create the 8.0.0 branch, RC1 tagged soon after. - 6 February, RC2 tag. - 27 February, Final tag, release shipping a few days after. What do you think, especially release testers? For the 6.0.0 release, the branch was created earlier in January after a request from the community. This time I haven't heard anything, but please let me know if a different schedule would be better for you. Ideally I'd like to finalize and post the schedule by the end of the week. Thanks, Hans _______________________________________________ lldb-dev mailing list [email protected] http://lists.llvm.org/cgi-bin/mailman/listinfo/lldb-dev
