On 12 Dec 2015, at 00:14, Hans Wennborg <h...@chromium.org> wrote:
> 
> It's not quite time to start the 3.8 release process, but it's time to
> start planning.
> 
> Please let me know if you want to help with testing and building
> release binaries for your favourite platform. (If you were a tester on
> the previous release, you're cc'd on this email.)

Hi Hans,

As usual, I will be taking care of the FreeBSD builds.  I think Ed Maste
will also be able to do some of the legwork.  (Specifically to get our
CMake build in shape. :)


> I propose the following schedule for the 3.8 release:
> 
> - 13 January: Create 3.8 branch. Testing Phase 1: RC1 binaries built
> and tested, bugs fixed. Any almost-complete features need to be
> wrapped up or disabled on the branch ASAP, and definitely before this
> phase ends.
> 
> - 27 January: Testing Phase 2: RC2 binaries built and tested. Only
> critical bug fixes from now on. Further RCs published as we approach..
> 
> - 18 February: Cut the final release, build binaries, ship when ready.

This schedule looks fine to me.

-Dimitry

Attachment: signature.asc
Description: Message signed with OpenPGP using GPGMail

_______________________________________________
lldb-dev mailing list
lldb-dev@lists.llvm.org
http://lists.llvm.org/cgi-bin/mailman/listinfo/lldb-dev

Reply via email to