o Teaching activity (2/10)

== Progress ==
o Linaro GCC (2/10)
   * Delivered 2016.01-1 Snapshot respin with fix for Linaro PR #2001
   * Gave some support on backports

o Infra/Validation (1/10)
   * Compared ABE master results.

o GCC dev. (2/10)
   * Identified the way testcases are uploaded on the remote target in
     cross validation as the root cause of validation instabilities.  Digging
     into GCC .exp files and DejaGNU to fix it cleanly.

o Misc (3/10)
   * Various meetings
   * Start a backport/validation document

== Plan ==
o Continue backports/validation document
o Continue on the ongoing cards opened