On holiday last week and at connect week before that.

==Progress===

* Recovered from jet-lag and started to catch up on email.
* Patch review week.
* Cleared out a bit of my patch backlog.
* Helped Asa with some bug triaging.
* Read up a bit about ssat and usat and what we should be doing with
other tuning for them.
* Looked up some performance profiles with v8 benchmarks . Reviewed the Android
benchmark numbers.
* Booked tickets for connect 2012.q2
* Wrote up connect week discussions on libav regressions .


=== Plans ===


* Clear out more pending patches ( PGO next on the hit list and the
vmla investigation)
* Investigate partial-partial PRE results.
* Finish off the ABI tests.


Absences.

* 1 week holiday sometime before that - to be booked.
* Linaro Connect Q2.12 - May 28 - June 1