https://bugs.kde.org/show_bug.cgi?id=432139

            Bug ID: 432139
           Summary: Re-scheduling an already scheduled sub-schedule with
                    started tasks not working
           Product: calligraplan
           Version: 3.3.0
          Platform: Other
                OS: Linux
            Status: REPORTED
          Severity: normal
          Priority: NOR
         Component: general
          Assignee: dag.ander...@kdemail.net
          Reporter: dag.ander...@kdemail.net
  Target Milestone: ---

SUMMARY
The actual start is disregarded and planned start is moved to the re-schedule
time.

First schedule of a sub-schedule works fine.

Work around:
1) Delete the sub-schedule
2) Create a new sub-schedule
3) Calculate the new sub-schedule

SOFTWARE/OS VERSIONS