https://bugs.kde.org/show_bug.cgi?id=414661

            Bug ID: 414661
           Summary: Can't add progress finish time in the past
           Product: calligraplan
           Version: 3.2.0
          Platform: unspecified
                OS: Linux
            Status: REPORTED
          Severity: normal
          Priority: NOR
         Component: usability
          Assignee: dand...@get2net.dk
          Reporter: t...@del.bg
  Target Milestone: ---

STEPS TO REPRODUCE
1. Finish some tasks (actual work done).
2. Open "Task Progress", click on "Finished".
3. Current date & time are automatically populated in the date time field.
4. A progress entry is created for the current date.

OBSERVED RESULT

5. I cannot change finished date to yesterday's date anymore.

EXPECTED RESULT

I should be able to set task's completion date to a time in the past.

-- 
You are receiving this mail because:
You are watching all bug changes.

Reply via email to