https://jira.codehaus.org/browse/MNG-5626?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Christian Jung updated MNG-5626:
--------------------------------

    Description: 
In issue MNG-5623 we reported an exception when printing the reactor summary if 
one of the times was negative.

I saw in one case, that the overall maven build time, as measured from outside 
(i.e. by our QuickBuild system) was -10.8 seconds. The corresponding reactor 
summary was:
{code}
13:55:25,184 INFO  - Reactor Summary:
13:55:25,184 INFO  -
13:55:25,184 INFO  - module1 ........................................... 
SUCCESS [ 5.911 s]
13:55:25,184 INFO  - module2 ........................................... 
SUCCESS [ 0.255 s]
13:55:25,184 INFO  - gpPlaygroundBase-lnx-x64-gcc4 ..................... 
SUCCESS [-27.-64 s]
13:55:25,185 INFO  - 
------------------------------------------------------------------------
13:55:25,185 INFO  - BUILD SUCCESS
13:55:25,185 INFO  - 
------------------------------------------------------------------------
13:55:25,185 INFO  - Total time: -20.-73 s
13:55:25,185 INFO  - Finished at: 2014-04-28T13:55:25+01:00
13:55:25,572 INFO  - Final Memory: 32M/439M
13:55:25,572 INFO  - 
------------------------------------------------------------------------
{code}
The thing is quite hard to reproduce, the machines were virtual machines that 
have been running for quite a long time.

Our administrators suspected that just at this point, the local clock was 
synchronized with some outer source.

We should check if such negative durations can be avoided, and if not, they 
should be handled correctly.




  was:
In issue MNG-5623 we reported a crash when printing the reactor summary if one 
of the times was negative.

I saw in one case, that the overall maven build time, as measured from outside 
(i.e. by our QuickBuild system) was -10.8 seconds. The corresponding reactor 
summary was:
{code}
13:55:25,184 INFO  - Reactor Summary:
13:55:25,184 INFO  -
13:55:25,184 INFO  - module1 ........................................... 
SUCCESS [ 5.911 s]
13:55:25,184 INFO  - module2 ........................................... 
SUCCESS [ 0.255 s]
13:55:25,184 INFO  - gpPlaygroundBase-lnx-x64-gcc4 ..................... 
SUCCESS [-27.-64 s]
13:55:25,185 INFO  - 
------------------------------------------------------------------------
13:55:25,185 INFO  - BUILD SUCCESS
13:55:25,185 INFO  - 
------------------------------------------------------------------------
13:55:25,185 INFO  - Total time: -20.-73 s
13:55:25,185 INFO  - Finished at: 2014-04-28T13:55:25+01:00
13:55:25,572 INFO  - Final Memory: 32M/439M
13:55:25,572 INFO  - 
------------------------------------------------------------------------
{code}
Our administrators suspected that just at this point, the local clock was 
synchronized with some outer source.

We should check if such negative durations can be avoided, and if not, they 
should be handled correctly.





> Avoid negative durations or handle them correctly
> -------------------------------------------------
>
>                 Key: MNG-5626
>                 URL: https://jira.codehaus.org/browse/MNG-5626
>             Project: Maven 2 & 3
>          Issue Type: Bug
>          Components: Logging
>    Affects Versions: 3.2.1
>            Reporter: Christian Jung
>            Priority: Minor
>
> In issue MNG-5623 we reported an exception when printing the reactor summary 
> if one of the times was negative.
> I saw in one case, that the overall maven build time, as measured from 
> outside (i.e. by our QuickBuild system) was -10.8 seconds. The corresponding 
> reactor summary was:
> {code}
> 13:55:25,184 INFO  - Reactor Summary:
> 13:55:25,184 INFO  -
> 13:55:25,184 INFO  - module1 ........................................... 
> SUCCESS [ 5.911 s]
> 13:55:25,184 INFO  - module2 ........................................... 
> SUCCESS [ 0.255 s]
> 13:55:25,184 INFO  - gpPlaygroundBase-lnx-x64-gcc4 ..................... 
> SUCCESS [-27.-64 s]
> 13:55:25,185 INFO  - 
> ------------------------------------------------------------------------
> 13:55:25,185 INFO  - BUILD SUCCESS
> 13:55:25,185 INFO  - 
> ------------------------------------------------------------------------
> 13:55:25,185 INFO  - Total time: -20.-73 s
> 13:55:25,185 INFO  - Finished at: 2014-04-28T13:55:25+01:00
> 13:55:25,572 INFO  - Final Memory: 32M/439M
> 13:55:25,572 INFO  - 
> ------------------------------------------------------------------------
> {code}
> The thing is quite hard to reproduce, the machines were virtual machines that 
> have been running for quite a long time.
> Our administrators suspected that just at this point, the local clock was 
> synchronized with some outer source.
> We should check if such negative durations can be avoided, and if not, they 
> should be handled correctly.



--
This message was sent by Atlassian JIRA
(v6.1.6#6162)

Reply via email to