Ilan Ginzburg created SOLR-14524:
------------------------------------
Summary: Harden MultiThreadedOCPTest
Key: SOLR-14524
URL: https://issues.apache.org/jira/browse/SOLR-14524
Project: Solr
Issue Type: Test
Security Level: Public (Default Security Level. Issues are Public)
Components: SolrCloud
Affects Versions: master (9.0)
Reporter: Ilan Ginzburg
{{MultiThreadedOCPTest.test()}} fails occasionally in Jenkins because of timing
of tasks enqueue to the Collection API queue.
This test in {{testFillWorkQueue()}} enqueues a large number of tasks (115,
more than the 100 Collection API parallel executors) to the Collection API
queue for a collection COLL_A, then observes a short delay and enqueues a task
for another collection COLL_B.
It verifies that the COLL_B task (that does not require the same lock as the
COLL_A tasks) completes before the third COLL_A task.
Test failures happen because when enqueues are slowed down enough, the first 3
tasks on COLL_A complete even before the COLL_B task gets enqueued!
In one sample failed Jenkins test execution, the COLL_B task enqueue happened
1275ms after the enqueue of the first COLL_A, leaving plenty of time for a few
(and possibly all) COLL_A tasks to complete.
Fix will be along the lines of:
* Make the “blocking” COLL_A task longer to execute (currently 1 second) to
compensate for slow enqueues.
* Verify the COLL_B task (a 1ms task) finishes before the long running COLL_A
task does. This would be a good indication that even though the collection
queue was filled with tasks waiting for a busy lock, a non competing task was
picked and executed right away.
* Delay the enqueue of the COLL_B task to the end of processing of the first
COLL_A task. This would guarantee that COLL_B is enqueued once at least some
COLL_A tasks started processing at the Overseer. Possibly also verify that the
long running task of COLL_A didn't finish execution yet when the COLL_B task is
enqueued...
* It might be possible to set a (very) long duration for the slow task of
COLL_A (to be less vulnerable to execution delays) without requiring the test
to wait for that task to complete, but only wait for the COLL_B task to
complete (so the test doesn't run for too long).
--