On Wed, Jun 2, 2010 at 1:51 PM, David Edelsohn <dje....@gmail.com> wrote: > On Wed, Jun 2, 2010 at 2:07 AM, Laurynas Biveinis > <laurynas.bivei...@gmail.com> wrote: >> Hello all - >> >> All the patches from gc-improv merge have been approved. Due to the >> scope of the changes, the merge will need trunk freeze. Thus I am >> planning to do it next Tuesday, at 7am CEST. The freeze should last >> about 2-3 hours. >> >> Alternatively I could also do the merge tomorrow at the same time, but >> I cannot give the 48h notice then. So unless I get a green light for >> tomorrow's merge, the next Tuesday it is. >> >> Here is the overview of the branch: >> http://gcc.gnu.org/ml/gcc/2010-04/msg00414.html > > Major merges should not freeze the trunk for hours but for a day. We > should ensure that the trunk is quiescent before the merge and allow > other developers to update and test before intermixing other patches.
Yes, I'd say we freeze late on Monday and unfreeze on Wednesday. Richard. > Thanks, David >