I noticed today that there were three projects which were merged into
the mainline within a 24 hour period yesterday.

Date: Thu, 19 Jan 2006 01:42:49 -0000  IAB  - Daniel Berlin
Date: Thu, 19 Jan 2006 10:24:04 -0000  Vect - Dorit
Date: Thu, 19 Jan 2006 16:55:54 -0000  GOMP - Diego Novillo

So I am requesting that we go through a 48 hour period starting Monday
(as the weekends are usually quiet for patch committing) for a stage 3
type regression only/bug fixes.

Right now we have some build regressions on some primary targets and there are about 25 regressions 4.2 (from 4.1) which have been reported already.

Two being wrong code and 6 being ICEs on valid code.

Thoughts?

Thanks,
Andrew Pinski