> As we build up the momentum to push an amazing 57 release out the door,
> below is a list of important milestones during Nightly57 and Beta57
> stabilization phase
> <https://docs.google.com/a/mozilla.com/document/d/1jeypuqBqEyIh-4qxXT0UnE2aVjetN7uVD8W7L7TbWKg/edit?usp=sharing>.
> This list includes dates for feature Go/NoGo, when to expect QA sign offs,
> release notes review, merge day, beta build cadence, RC week, etc.
>
> I will add these high-level milestones into Sheila's 57 track back
> schedule document by end of this week. Please let me know if there are any
> questions/concerns or if this list is missing a key milestone. Thanks!
>
> Nightly 57 milestones
>
> Date
>
> Title
>
> Details
>
> 8/22
>
> Features in testable shape
>
>    -
>
>    Most of dev implementation is complete
>    -
>
>    The feature is in a position to be tested - functionally/perf.
>    -
>
>    Ready to be turned on by default in Nightly.
>
> 8/28 - 9/1
>
> Mid-nightly feature sign off
>
> Week of 9/11
>
> All 57 “QF:P1” blockers fixed
>
>    -
>
>    Anything beyond this milestone will add huge risk to Beta57 quality
>    -
>
>    One mitigation is to require engg mngr approval for any fixes landing
>    the week of 9/18 until 9/27 (57.0b1 pushed)
>
>
> 9/19
>
> Nightly features Go/No Go decisions
>
> 9/21
>
> Nightly -> Beta Merge
> Thursday before go live
>
> 9/22
>
> Beta57 release notes draft
>
> Recurring milestones
>
> Every 2 weeks
>
> Nightly smoke testing
>
>    -
>
>    Week 2, 4, 6 and 8
>
>
>    -
>
>    Photon, Stylo, Activity Stream, Web extensions
>
> Weekly
>
> Perf tests
>
> Weekly
>
> PI Risk report
>
> Weekly
>
> Quantum release criteria
>
>
>
> Beta 57 milestones
>
> Date
>
> Title
>
> Details
>
> 9/21
>
> Nightly -> Beta Merge
> Thursday before go live
>
> 9/25
>
> Beta1 gtb
>
> 9/27 - 10/6
>
> Beta Staged rollout
>
> 57.0b2, b3, b4 gtb, push
>
> 10/9 - 10/10
>
> 100% of Beta rollout
>
> Beta5 gtb, push
>
> By Beta 4
>
> All planned experiments have been kicked off
>
> Starting experiments late jeopardizes their ability to add value
>
> 10/23
>
> Feature Go/NoGo decisions
>
> 10/17 is 57.0b9 gtb
>
> 10/30 - 11/3
>
> Pre-beta sign offs
>
> 11/6 - 11/10
>
> RC week
>
> 11/8
>
> Release 57 notes
>
> 11/14
>
> Go Live
>
> Recurring milestones
>
> Mon - Tue
>
> Gtb, push beta build
>
>    -
>
>    Desktop
>    -
>
>    Fennec
>
> Thu - Fri
>
> Gtb, push beta build
>
>    -
>
>    Desktop only
>
>
_______________________________________________
dev-platform mailing list
dev-platform@lists.mozilla.org
https://lists.mozilla.org/listinfo/dev-platform

Reply via email to