On 7/30/24 09:53, imtoas...@mail.com wrote:

[Message resent because the year was wrong]

Dear all,

We are currently considering the following dates as our freeze
dates. If you are aware of major clashes of these dates with anything
we depend on please let us know. We also like to stress again that we
really would like to have a short Hard and Full Freeze (counting in
weeks, rather than months), so please plan accordingly. If serious
delays turn up during any of the Freeze steps, we rather (partially or
completely) thaw bookworm again than staying frozen for a long time.

2023-01-12      - Milestone 1 - Transition and toolchain freeze
2023-02-12      - Milestone 2 - Soft Freeze
2023-03-12      - Milestone 3 - Hard Freeze - for key packages and
                                packages without autopkgtests
To be announced - Milestone 4 - Full Freeze

On behalf of the Release Team,
Paul