- Increase the post-release ("cool down") margin before we open the feature
window. We currently have it 5 days, we could double it to 10 days. That
would then reduce the feature window with the same amount of days leaving
us with 18 days to merge features.
I did not spot any complaints on that suggestion so I figure we should move in
that direction.
Another adjustment to the cycle I think we can do is to even out the feature
window and the feature freeze periods a little. A full three weeks for new
features:
Like this:
RELEASE (on a Wednesday)
10 days cool down (possiblity to decide to do a patch release)
FEATURE WINDOW (assuming nothing bad disturbed the peace)
21 days
BUG-FIX PERIOD
25 days of no new features/changes
RELEASE (on a Wednesday)
--
/ daniel.haxx.se
| Commercial curl support up to 24x7 is available!
| Private help, bug fixes, support, ports, new features
| https://curl.se/support.html
--
Unsubscribe: https://lists.haxx.se/mailman/listinfo/curl-library
Etiquette: https://curl.se/mail/etiquette.html