Actually, given the delay we had with getting the kickstarter started, I would like to plan the 2.9 release for around December. And then in January start on the Qt5 port with a 3.0 release around March, April.

On Tue, 24 Jun 2014, Cyrille Berger wrote:

Hello,

We never quiet reached a conclusive answer to that thread... But since it is getting "late", I guess we would go for my original suggestion:

- branch early august, around August 10th
- release final in September

Also, since the 2.8 branch seem to still be rather active, I guess we could schedule a 2.8.5 for early August.

--