I want to develop and run my parallel code (MPI based) on a Beowulf cluster. I 
have no problem as such that many user might log on to the cluster 
simultaneously. Suppose that I am free to use cluster dedicatedly for my single 
parallel application. 
 
1) Do I really need a cluster scheduler installed on the cluster? Should I use 
scheduler?
[Bill Bryce] If you are the only user of the cluster then you don't *really* 
need a scheduler, however if you want to queue up lots of jobs on your cluster 
and 'just let it run' then a scheduler is needed. 
 
2) Is there any effect/benefit on the running of a parallel code with or 
without cluster job scheduler?
[Bill Bryce] There are some benefits.  Most schedulers/resource managers are 
integrated with various implementations of MPI so that task startup and task 
cleanup is controlled by the scheduler/resource manager.  What this means for 
you is less time spent cleaning up dead processes on the nodes in your cluster. 
 Schedulers and resource managers also have job control which allows you to 
suspend and resume the entire parallel job - sometimes this is useful.
The scheduler and resource manager are really useful when you want to run many 
jobs on your cluster - when this happens the scheduler will decide which nodes 
in the cluster will be allocated for your parallel job based on the scheduling 
policy (or policies) enabled in the scheduler.  Overall a good scheduler and 
resource manager combination will keep the whole cluster busy running your work 
whereas manually running jobs relies on *you* to be the scheduler which is not 
as efficient as a scheduler.
 
One of the distinct advantages of a scheduler/resource manager is when things 
go wrong.  All scheduler/resource managers provide mechanisms to handle job 
failure, host failure and re-running the job automatically.  So if your job 
fails at say 3 in the morning the system will automatically recover and start 
your work over again. 
 
3) How you differentiate between cluster scheduler and cluster resource manager?
[Bill Bryce] 
I'm sure you'll get more responses on this question but here is my two cents 
worth....
 
The cluster scheduler is only concerned about scheduling work to the available 
resources (or future availablity of resources), so FCFS, Fairshare, Backfill, 
pre-emption, Quality of Services, are all valid scheduling policies used by a 
scheduler to determine when your job will run and what resources the job will 
use to run on the cluster.
 
The resource manager is responsible for discovering, monitoring and aggregating 
resources in your cluster, so that this information can be used by the 
scheduler to make decisions.  Resources can be pretty much anything, but to 
keep it simple resources are the hosts, cpus, cores, memory, network 
interfaces, etc... 
 
 
 
4) If there is any significant difference between a scheduler and manager then 
plaese tell me that which of the fall in which category:
[Bill Bryce] 
Ah now this is where, depending on who you talk to; you get different 
answers... 
 
OpenPBS, PBSPro, SGE, LSF, Torque - are all both resource managers and 
schedulers.
 
Maui & Moab are Schedulers - and require a resource manager (so one of the 
above)
 
Scyld - is much more than just a resource manager/scheduler it is an entire 
collection of software for running a Beowulf cluster - you could say Scyld is 
the whole 'cluster stack of software'.  Resource managers and Schedulers can 
run on a Scyld cluster.
 
SLURM - is a resource manager and is quite good at doing resource allocations 
for parallel jobs.  SLURM is used in conjunction with a Scheduler (or one of 
the Scheduler/Resource managers)
 
OpenPBS, PBS Professional, SGE, Maui, Moab, Torque, Scyld, LSF, SLURM etc.
 


 5) What is maent by  " PBS/SGE/LSF supports integration with the Maui 
scheduler?
[Bill Bryce] 
It simply means that Maui can sit on top of PBS/SGE/LSF and 'take control of 
scheduling' by turing off or ignoring the built in scheduler in PBS/SGE/LSF.  
 
Regards, 
 
Bill.
 
 
 
Precise, easy and brief reply requested. Thanks to all. 
 
 

_______________________________________________
Beowulf mailing list, Beowulf@beowulf.org
To change your subscription (digest mode or unsubscribe) visit 
http://www.beowulf.org/mailman/listinfo/beowulf

Reply via email to