On 24. 4. 2013 Konrad Zemek wrote: > September 09 - 15: > Implementing two-way synchronization for remaining importers. > September 16 - 22: > Ironing out bugs, writing remaining tests. Cushion period in > case of delays. > September 23 - 29: FINAL EVALUATION > Ironing out bugs, writing remaining tests. Cushion period in > case of delays. Submitting work for final evaluation
Please be aware of the fact that Sep 23 is the "firm pencils-down" date, so a cushion week 23 - 29 is actually a bit late. As Sep 16 is the "suggested pencils-down" date, it may have sense to target having all the work incl. tests done by that date. [this year's GSoC seems about 3 weeks longer than previous ones, am I right?] Matěj _______________________________________________ Amarok-devel mailing list Amarok-devel@kde.org https://mail.kde.org/mailman/listinfo/amarok-devel